Agreement Title
Route 11 (Section between Yuen Long and North Lantau) – Feasibility Study
Commencement Date
May 2018
Scope
  • Engineering feasibility and infrastructure study;
  • Alignment options study;
  • Port operations, and marine traffic impact and safety study;
  • Preliminary environmental review and preparation works for the environmental impact assessment;
  • Consultation exercises with relevant stakeholders and the public; and
  • Preliminary site investigations.
Consultant Name
Meinhardt - Aurecon Joint Venture
Progress
Basically completed

Implementation Programme

Feasibility Study

  • Engineering feasibility and infrastructure study;
  • Alignment options study;
  • Port operations, and marine traffic impact and safety study;
  • Preliminary environmental review and preparation works for the environmental impact assessment;
  • Consultation exercises with relevant stakeholders and the public; and
  • Preliminary site investigations.

Investigation Study

  • Review of the findings of previous studies;
  • Examination of alignments and design options;
  • Impact assessments on traffic, heritage, land and other related aspects;
  • Environmental impact assessment pursuant to the Environmental Impact Assessment Ordinance;
  • Gazette pursuant to the Roads (Works, Use and Compensation) Ordinance;
  • Preliminary design; and
  • Site investigations.

Detailed Design and Construction Stages

  • Review of previous preliminary design;
  • Detailed design;
  • Tendering works; and
  • Construction.

Anticipated Commissioning Date

We target to commission the entire group of major roads (including Route 11, Tsing Yi-Lantau Link and the widening of Yuen Long Highway (Section between Lam Tei and Tong Yan San Tsuen)) not later than 2036.

Implementation Programme

2018 - Feasibility Study

  • Engineering feasibility and infrastructure study;
  • Alignment options study;
  • Port operations, and marine traffic impact and safety study;
  • Preliminary environmental review and preparation works for the environmental impact assessment;
  • Consultation exercises with relevant stakeholders and the public; and
  • Preliminary site investigations.

2021 - Investigation Study

  • Review of the findings of previous studies;
  • Examination of alignments and design options;
  • Impact assessments on traffic, heritage, land and other related aspects;
  • Environmental impact assessment pursuant to the Environmental Impact Assessment Ordinance;
  • Gazette pursuant to the Roads (Works, Use and Compensation) Ordinance; and
  • Preliminary design and site investigations.

Detailed Design and Construction Stages

  • Review of previous preliminary design;
  • Detailed design;
  • Tendering works; and
  • Construction.

2036 - Anticipated Commissioning Date